StoryPublic Safety campus construction timeline and project detailsJune 4, 2025

Woodbury Public Safety Campus Construction Set for Spring 2026

Meeting date: Jun 4, 2025
Published Jul 2, 2025

Woodbury will begin construction on its Public Safety campus remodel and expansion project in spring 2026, with completion expected in 2028, city officials announced during a recent council update.

The project addresses overcrowding and inadequate facilities at the current campus, which officials said cannot meet increased demands on staff and emergency services. The expansion will add a second level above part of the new structure and extend south to incorporate the soon-to-be vacated Washington County Service Center on Central Park Place.

Emergency Medical Services and Fire vehicle access will be relocated further south at the existing traffic signal at Central Park Place and Radio Drive to improve controlled access. The public parking lot and building entrance will move to the north end of the property to accommodate the changes.

Funding for the project comes from a voter-approved 0.5% sales tax that began in April, grants, and a $13 annual property tax increase. The sales tax will generate up to $50 million over 20 years specifically for the project, with funds dedicated solely to the campus construction.

During construction, limited public safety administrative services will be provided at City Hall, while emergency police, fire and medical services will continue from various locations including fire stations. Some public safety operations will temporarily move to the former Washington County Services building after the county relocates to its new Woodlane Drive facility in November. Construction bidding is scheduled for late fall 2025.

Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.

Go deeper on this topic

Research related meeting documents and build a brief — without rewriting the story.

Full analysis
  • Expansion of public safety facility despite environmental site constraints involving adjacent wetlands.
  • Strategic use of former Washington County Service Center to house public safety operations during construction.
  • Funding reliance on a 0.5% sales tax capped at $50 million or 20 years to finance critical public safety infrastructure.
  • Potential service disruptions and logistical shifts for emergency vehicle response during the 2026-2028 construction period.
Source document

As you might recall, we anticipate beginning the remodel and expansion of our public safety campus in spring 2026. At our May 28th workshop, staff updated the city council on the project's progress and shared preliminary renderings of the building. It seems like an appropriate time to share some project updates with you. With the adjacent wetlands behind the building to the west, the site offers some unique challenges for expansion. To accommodate the need for more space, a second level will be added above part of the new structure and the campus will be expanded to the south where the soontobe vacated existing Washington County Service Center sits. Emergency medical services and fire vehicle access will be moved further south at the existing traffic signal at Central Park Place and Radio Drive to improve controlled access to Radio Drive. The public parking lot and building entrance will be moved to the north end of the property. The project is needed to ensure that the city continues to deliver the highest possible levels of public safety. The current facility is overcrowded and inadequate for emergency vehicle response and does not position us for success as we experience increased demands on our staff, programs, and emergency services. We are committed to maintaining highquality public safety services throughout this transition. Additional details about service adjustments will be shared as they become available. Limited public safety administrative services will be provided at city hall during construction. Emergency police, fire, and medical services will continue to be maintained at a high level from different locations around the city, such as at our fire stations. Furthermore, as part of the construction, some public safety operations will temporarily move to the former Washington County Services Building. Washington County plans to move to its new service center on Woodlane Drive in November. At that time, we will begin transitioning the vacant space for temporary use by public safety personnel. We appreciate the public support of this project through the November 2024 referendum. The project will be primarily funded through a.5% sales tax that began in April. Funds from this sales tax will be dedicated solely to the project and will end when the funding reaches $50 million or in 20 years, whichever comes first. We see the sales tax as a shared investment because residents and visitors alike will share in funding the public safety services that they use. The remaining project funding will come from grants along with a $13 annual increase in property taxes. The city continues to refine the building design and site layout of the public safety campus with anticipated construction bidding in late fall. The new public safety campus is expected to reopen in 2028. Look for more detailed information on the city website and in future editions of the Woodbury City Update newsletter. Thank you again for your ongoing support of our first responders.

Was this story helpful?

Other Topics from This Document

  • Public safety campus expansion and remodel

  • Site design and logistics challenges

  • Emergency service adjustments during construction

  • Project funding through sales tax and property taxes

  • Relocation of public safety operations