[0:01] Hi, John Nelson, assistant city engineer [0:03] with the city of Lakeville. Here to talk [0:05] to you today about active road projects [0:07] going on within the city. We have the [0:10] 202nd Street and Hamburg Avenue [0:13] intersection improvement project. This [0:15] will be construction of a single lane [0:18] roundabout at the intersection of 202nd [0:21] Street and Hamburg Avenue. The [0:24] roundabout is being constructed due to [0:26] the need for a safety improvement at the [0:28] intersection and is necessary to help [0:30] provide safety throughout the community [0:32] with substantial completion targeting a [0:35] midepptember completion date and [0:37] intersection reopening at that time. [0:40] 185th Street construction is actively [0:43] underway. Construction is proceeding on [0:46] schedule for that project. We are still [0:49] targeting a substantial completion date [0:51] at the beginning of September. 185th [0:54] Street and IPava intersection is [0:57] reopened to traffic at this time. Uh [1:00] utilities, curbon gutter, and the first [1:03] course of asphalt pavement have been [1:05] installed throughout the east end of the [1:07] project between Exonia Avenue and IPA [1:11] Avenue. We are now beginning work on the [1:14] west end of the project between County [1:17] Road 50 and Exonia Avenue, starting from [1:21] the ground up with utility [1:22] installations. For more information, go [1:25] to lakevillemn.gov [1:26] for additional information on our city [1:28] projects. [1:31] [Music]

Stories from this meeting (2)

Document Analysis

No minutes document found yet. Refresh ingestion to check for newly published minutes, or analyze the agenda packet alone.

Topics Discussed (1)

Active Road Projects Update

Full Document Analysis
No official action or vote recorded as this was a project update.

This will be construction of a single lane roundabout at the intersection of 202nd Street and Hamburg Avenue.

John Nelson/Assistant City Engineer [0:15]Active Road Projects Update

The roundabout is being constructed due to the need for a safety improvement at the intersection and is necessary to help provide safety throughout the community.

John Nelson/Assistant City Engineer [0:24]Active Road Projects Update

Construction is proceeding on schedule for that project. We are still targeting a substantial completion date at the beginning of September.

John Nelson/Assistant City Engineer [0:43]Active Road Projects Update