StoryRailroad Crossing Safety Improvements in EdinaJune 13, 2026

Edina seeks federal funds for railroad crossing safety study

The Edina City Council is pursuing $200,000 in federal funding to study safety improvements at seven railroad crossings operated by CPKC Railroad. The move comes as increased nighttime train operations have raised concerns about noise and safety in the community.

Meeting date: Mar 17, 2025
Published Jun 13, 2026

The city is developing a Railroad Crossing Safety Action Plan to address the seven at-grade crossings — places where roads cross railroad tracks at the same level — that run through Edina on the CPKC Railroad line. The study, estimated to cost $250,000, would evaluate whether any crossings can be eliminated entirely, whether grade separation improvements are feasible, or what safety measures should be implemented. The city has requested $200,000 in federal funding to help cover the cost, with a decision expected by March 2025.

If crossings cannot be eliminated, the study would examine specific safety mitigation options including pavement markings to show where cars should stop, flashing lights, crossing signage, and overhead arms that stop traffic when trains approach. These improvements are designed to reduce accidents and injuries at the crossings.

The council also discussed growing noise complaints from train horns, which federal regulations require to sound 15 seconds before trains enter public crossings. While the city explored establishing "quiet zones" to eliminate horn requirements, council members learned that the Federal Railroad Administration must approve any quiet zone designation — a process that takes multiple years. Importantly, the city would first need to implement safety mitigation measures at each crossing before the federal agency would even consider approving a quiet zone.

As one council member explained, the approach is hierarchical: "we have to first study if we can eliminate any of the crossings and if we can't then what can we do to mitigate the risks." This means residents should not expect immediate relief from train horn noise, but the safety study represents a first step toward longer-term solutions for both safety and noise concerns.

Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.

Go deeper on this topic

Research related meeting documents and build a brief — without rewriting the story.

Full analysis

Notable Quotes (3)

we have to first study if we can eliminate any of the crossings and if we can't then what can we do to mitigate the risks

— Unknown [Timestamp]
Federal Funding Request for Railroad Crossing Safety Action Plan

to mitigate the risks are pavement markings to show where cars are supposed to stop before they cross the tracks we can do flashing lights we can do Crossing signage or just overhead arms that stop traffic when a train comes through

— Unknown [Timestamp]
Federal Funding Request for Railroad Crossing Safety Action Plan

if the city wants to establish a quiet Zone that has to be approved by the Federal Railroad Administration they have to look at the RIS the mitigation risk tactics that we want to do at each Crossing we would have to implement those mitigation risk improvements and then we would be able to implement that quiet Zone with them and through them that process is a multi-year Endeavor

— Unknown [Timestamp]
Federal Funding Request for Railroad Crossing Safety Action Plan

Ordinances & Resolutions (2)

Railroad Crossing Safety Action PlanPlan

Proposed study to evaluate elimination, grade separation improvements, or safety mitigation measures for seven at-grade crossings in Edina; estimated cost $250,000 with $200,000 federal funding requested

Federal Railroad Administration Quiet Zone Approval ProcessOther

Multi-year regulatory process required to establish quiet zones; requires risk mitigation implementation and FRA approval before horn requirements can be eliminated

Source document

Was this story helpful?

Other Topics from This Document

  • Train Horn Noise and Quiet Zone Establishment