Power Line Issue Threatens Highway 100 Project Timeline
An unexpected power line conflict could delay completion of Edina's Highway 100 and Vernon Avenue interchange project, officials revealed during Thursday's bi-weekly project update meeting.
The Excel Energy power line, located near the west support of the Vernon Avenue bridge, was discovered to be in a different position than construction plans indicated. The issue requires new permits and agreements between Excel Energy and CPKC Rail, potentially causing significant delays if not resolved within weeks.
This is a major concern from the project schedule standpoint,' the project manager explained during the virtual meeting. 'It has delayed construction operations and could make some major delays if something isn't addressed in the next few weeks.
Separately, the project team announced plans to begin closing highway ramps as early as mid-July. The closures, affecting both east and west ramps, may be implemented on different schedules. Officials promised detailed communications and updated detour information once dates are finalized.
The project, which includes bridge reconstruction and ramp consolidation, maintains its target completion date of mid-November 2025. Construction crews are currently making progress on bridge supports and median work, with concrete pouring operations occurring primarily at night to minimize traffic disruption.
Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.
Go deeper on this topic
Research related meeting documents and build a brief — without rewriting the story.
Full analysis
- Construction delay risk due to misidentified Xcel Energy utility lines in rail right-of-way.
- Public frustration regarding school drop-off traffic and construction overlap.
- Substantial project completion scheduled for November 15, 2025, conflicts with school year.
- Uncertainty regarding ramp closure schedules and potential noise wall impacts for residents.
This is a major concern from the project schedule standpoint... it could make some major delays if if something isn't addressed.
Give yourself extra time You need extra time to get in and out of that school campus to drop kids off pick up kids.
The completion date that was in the bid documents was November 15 2025.
Source document
[0:00] uh meeting number seven highway or the
[0:03] Vernon Avenue and Highway 100
[0:04] interchange project meeting number seven
[0:06] We are recording this Uh thank you again
[0:09] for the patience with the project
[0:11] Businesses are open and accessible
[0:14] All the normal construction stuff
[0:15] continues Dust noise vibrations Uh
[0:18] please stop for pedestrians and
[0:19] crosswalks We got some roads with higher
[0:22] traffic volumes with crosswalks Please
[0:24] be courteous to the pedestrians and to
[0:27] fellow drivers uh on these cross streets
[0:30] that are trying to get into a few of
[0:31] those roundabouts on Eaton Avenue
[0:34] Goals of the project show this every
[0:36] time uh improve safety mobility of all
[0:38] users improve traffic operations create
[0:41] separated pedestrian routes consolidate
[0:44] points then a few other uh goals there
[0:48] Project timeline is shown on the bottom
[0:52] So looking at substantial completion mid
[0:55] November We'll talk a little bit about
[0:56] schedule in a later slide here
[1:00] This is the project location Again it
[1:02] goes from just west of Interlockan
[1:03] Boulevard on Vernon to placing the
[1:06] Vernon Avenue bridge over the railroad
[1:09] consolidating and cleaning up the on
[1:10] andoff ramps of Highway 100 redoing the
[1:13] Highway 100 bridge and then tying into
[1:16] the city project just west of Graange
[1:18] Road from last year
[1:22] lots of communications We continue to
[1:24] use all these uh channels Again go to
[1:28] the better together edina.org
[1:31] backon-i100
[1:33] for all the project updates and
[1:36] materials Sign up for those email
[1:38] project updates U you'd like me to come
[1:41] speak anywhere let me know We can set up
[1:44] special meetings I've have met with
[1:46] various different business groups in the
[1:48] past and willing to do that again Uh the
[1:50] map on the bottom is where we stand
[1:53] today from a traffic control standpoint
[1:56] So that has not changed since early May
[1:59] when we initiated kind of that stage two
[2:02] traffic changes
[2:05] So today we're uh this is focusing more
[2:07] on the uh interlock and Vernon
[2:09] intersection It is free flowing They've
[2:11] did some work here last week to remove
[2:13] the median and pave it for earlier this
[2:16] week It is still free flowing you're
[2:18] just going to see traffic lanes being
[2:20] moved and adjusted so they can do
[2:23] underground utility work storm sewer
[2:25] pipes um and stuff like that that
[2:27] underground in the need room to do some
[2:29] trenching and excavation to install
[2:32] pipes So this is still going to be open
[2:34] It'll just be shifted Again Gus Young
[2:36] Lane is closed at Adina Liquor Store Um
[2:39] there will be work in front of the Adina
[2:42] liquor store starting on Monday next
[2:46] week Monday June 30th in that circled
[2:48] area We're redoing all the sidewalks the
[2:51] front entrance making that ADA compliant
[2:53] That will impact the parking lot
[2:56] landscaping the sidewalks that are there
[2:57] today So that work is starting next week
[3:01] and we're going to wrap that up so we
[3:03] can reopen the store in a few weeks So
[3:06] just note that that store is going to be
[3:07] closed starting Monday Please visit the
[3:09] other AD liquor stores in town
[3:14] Uh I'm going to make you aware of some
[3:15] some issues we're seeing with the west
[3:19] support of the Vernon Avenue bridge So
[3:21] this is the support that's uh near
[3:23] Holiday near the Adina liquor store Um
[3:27] in that green circle is an Excel power
[3:29] line It was horizontally and vertically
[3:32] different than what Asbuilts had shown
[3:36] And this picture shows it got hit and it
[3:39] was re repaired right after the hit but
[3:42] it's still in the railroad right away
[3:46] There's an old 1968 agreement for an
[3:48] aerial line between those two parties It
[3:51] does not cover this line
[3:54] Both agencies are talking but they both
[3:56] are requiring permits new agreements
[3:59] Whether that's a temporary move of that
[4:01] line making it deeper moving around it
[4:04] getting it out of the rightway doesn't
[4:06] matter Temporary or permanent permits
[4:09] and agreements are needed from both
[4:11] Excel Energy and CPKC Rail to adjust
[4:15] that line
[4:17] This is a major concern from the project
[4:20] schedule standpoint Um
[4:23] it has delayed construction operations
[4:26] and it could make some major change
[4:29] major delays if if something isn't
[4:32] addressed in the next few weeks Uh there
[4:34] won't be the ability to kind of catch up
[4:36] of some time of some construction
[4:39] operations that were supposed to be
[4:40] occurring now So Edina Hannipan County
[4:43] and Mindot all the project teams as
[4:46] construction we have no control over
[4:47] these two agencies They are working
[4:50] They're talking That's good Um but their
[4:53] time frames to get this all approved is
[4:56] kind of unknown at this point So we are
[4:59] pushing on a pretty much daily basis to
[5:01] get this stuff done so we can get the
[5:04] thing moved and continue operations on
[5:06] this west bridge support Um like I
[5:09] mentioned we have a few weeks to figure
[5:11] this out and before some major impacts
[5:14] to the schedule could occur
[5:17] Another thing that's likely to change
[5:19] pretty soon So we knew we had to close
[5:21] ramps at some point within the project
[5:24] Um so there's some preliminary
[5:25] discussions on schedule for when we want
[5:28] to do the ramp work When should we start
[5:31] implementing this ramp work shown in the
[5:34] yellow and that would close those ramps
[5:37] Um there may be different schedules for
[5:40] the east ramps on the city hall side
[5:42] versus the west ramps on the Devon or
[5:46] Holiday side So those schedules are
[5:48] still being developed by the contractor
[5:52] Could be as soon as mid July So two
[5:54] three weeks roughly Uh we'll know more
[5:57] next week And once we know more and have
[6:00] some more set dates we'll start creating
[6:04] the maps creating outreach
[6:06] communications all the stuff we did with
[6:08] the stage two traffic changes
[6:11] If the ramps on the east side are closed
[6:15] that would also be the opportunity to
[6:16] build that noise wall that goes on along
[6:20] that northbound Highway 100 on-ramp So I
[6:23] know the residents in that area are very
[6:24] interested about that noise wall So once
[6:27] we can confirm dates we will reach out
[6:29] to those individual properties there on
[6:32] Sunny Slope Road West
[6:36] and there will be detour modifications
[6:39] right with these closures Um we'll
[6:42] update those detours There may be some
[6:45] tweaks to the detours that were in the
[6:47] original plans Uh we've learned some
[6:49] things so we'll be making some
[6:50] modifications to those We want to keep
[6:53] the project moving So this is another
[6:54] way to continue building as much as we
[6:57] can now Um and it was going to happen at
[7:00] some point So we may start to look at
[7:02] this mid July So more to come on
[7:04] potential traffic changes coming soon
[7:07] And then some pictures We share pictures
[7:09] every every other week because you can't
[7:11] get down here to get these pictures So
[7:13] Dererick's been taking some great
[7:14] pictures Uh the picture on the left
[7:18] you're on the east side of the highway
[7:20] City Hall is kind of behind you or the
[7:21] Graange Historic Buildings are behind
[7:23] you So that's the supports starting to
[7:25] get ready to pour concrete for the east
[7:28] bridge supports You can see the median
[7:30] supports are going up and then across is
[7:33] the west side Bottom right hand corner
[7:35] is a closeup of that median work uh
[7:38] that's happening uh some during the day
[7:41] some with some lane closures during the
[7:42] day between certain hours mostly pouring
[7:46] concrete at night and build that median
[7:49] center supports for the bridge
[7:52] Then here's a closeup of the forms and
[7:54] and some concrete that has been poured
[7:56] on the west side for that high under
[7:59] bridge
[8:03] And here's what that looks like when
[8:04] they do that work So they got concrete
[8:06] trucks parked at top a big concrete
[8:07] pumper truck The picture on the left
[8:10] shows kind of that full picture The one
[8:12] on the right Zooming in on that pumper
[8:15] truck arm that's supplying the concrete
[8:18] into the big forms for the bridge You
[8:21] can see the scale with a few worker AIM
[8:24] employees there uh within those areas
[8:29] Switching to the other bridge uh the
[8:32] Vernon Avenue over the rail bridge So
[8:34] we're looking at Devani's on the right
[8:36] hand side looking east This was a
[8:39] picture I shared two weeks ago of that
[8:41] area where they started to put in the
[8:43] supports to protect that building That
[8:46] was two weeks ago Picture on the right
[8:49] is today or yesterday So you can see the
[8:53] supports the lagging to support the soil
[8:55] for the building Devonti's building and
[8:57] then the forms for the big spread
[9:00] footing for that new bridge on the east
[9:01] side So you can see that work starting
[9:05] on the east side of this Vernon Avenue
[9:06] bridge
[9:08] Here's that same thing but looking west
[9:10] So you can see the holiday sign in the
[9:13] background So that's gives you a scale
[9:16] with those three employees walking in
[9:18] that area of the size of the foundation
[9:20] for the bridge Vernon Avenue Bridge on
[9:22] the east side You look across the tracks
[9:25] We would like to see the same forms on
[9:27] the other side of the tracks but it's
[9:30] not there because of that Excel power
[9:32] line that's causing some issues with
[9:35] operations on the west side So if we
[9:38] were going to plan this we would have
[9:39] wanted both those being happening at the
[9:41] same time That side is in that uh
[9:44] holding pattern until XL Energy and CPKC
[9:47] Rail can figure out the permits and
[9:48] agreements
[9:51] And then again this is some renderings
[9:53] of the finished product of the Highway
[9:54] 100 bridge On the left is up at the
[9:57] bridge looking west with the big wide
[9:59] sidewalks additional turn lanes
[10:02] railings push buttons for the
[10:04] pedestrians and then on the right hand
[10:06] side is a view from the highway itself
[10:09] going northbound
[10:14] So with that I'd be happy to take any
[10:16] questions either in the chat or Yeah I
[10:20] think we can only do the chat So if you
[10:22] got questions put them in the chat and
[10:24] we'll read those off
[10:26] as they pop up
[10:29] Any questions
[10:33] chad could you say a little bit more
[10:34] about the um power line that was in the
[10:36] wrong spot like for example is there any
[10:39] disruption to the businesses
[10:42] the street lights or the you know the uh
[10:44] traffic signals or to the neighbors
yeah
[10:47] great question So it was hit So when it
[10:50] was hit there was uh Excel has a
[10:52] redundant system So the down time was
[10:55] was short They could supply power from
[10:58] other directions and then they came in
[11:00] immediately and have patched that back
[11:02] together So that that line is operating
[11:05] Um we're at peak demand right 90 90
[11:08] degree weather last week Um this line is
[11:11] needed to supply power within the in
[11:14] this district for all the agencies and
[11:16] people you just mentioned So um it was a
[11:19] short time outage Um and now when they
[11:22] do the tie over or the temporary
[11:26] solution or the permanent solution
[11:28] they'll again work with Excel on um how
[11:32] that operates with their needs for power
[11:34] in the area at this time of year We
[11:37] don't want to shut power off to anybody
[11:38] I guess is what I'm saying
[11:42] Uh there was a question in
[11:47] the chat Will there be a gap between the
[11:50] old wall by the Hawthorne condos and the
[11:53] new wall going up on Hawthorne Court uh
[11:57] no The old wall the new wall they're
[11:58] going to connect to each other at the
[12:00] point where it was removed So that'll be
[12:02] all connected when complete Be one
[12:04] continuous noise wall again after the
[12:06] project
[12:09] And another question I have a question I
[12:11] have a OG student
[12:14] With the project increasing traffic how
[12:16] will this project affect drive times and
[12:18] safety to the school yeah we saw that
[12:21] happen in in May um when school is when
[12:26] kids are getting dropped off for school
[12:28] or the buses are trying to enter that
[12:30] site or at pickup time So morning and
[12:32] afternoon uh it's a mess Uh Eden Avenue
[12:36] is doing a good job with normal traffic
[12:38] operations when the push for students in
[12:40] the school in the morning and PM happen
[12:43] Um I would say give yourself extra time
[12:46] You you need extra time to get in and
[12:48] out of that school campus
[12:52] to drop kids off pick up kids whatever
[12:54] you need to do with your student at OOLG
[12:56] So uh that'll be more in the fall when
[12:59] when you have to do that
[13:02] Great question
[13:06] Other questions
[13:11] again appreciate everybody for waiting
[13:13] Sorry I was late uh to kick this off
[13:15] this time
[13:18] Again my information is on the Better
[13:19] Together Dina website if you got
[13:21] specific questions Call me email
[13:25] whatever you need in regards to this
[13:27] project
[13:29] Uh will they work Saturdays all through
[13:31] the project
[13:33] um they're allowed to work Saturdays
[13:35] That's really a contractor question I'm
[13:36] I'm not sure if they plan to do it every
[13:38] Saturday or not Um
[13:43] that's really up to them They're allowed
[13:44] to do that So
[13:46] can't answer if they plan to do that
[13:48] through the entire project or not
[13:51] Uh will the school will the project be
[13:53] completed by the start of school no Uh
[13:56] the completion date that was in the bid
[13:58] documents was November 15 2025
[14:02] Um so that's the date right now as we
[14:04] know it and if anything changes we'll
[14:07] communicate that out I mentioned the one
[14:09] thing that's concerning of the project
[14:11] team at this point is that Excel Energy
[14:13] Line and how that may or may not in fact
[14:16] impact the schedule but no the project
[14:19] will not be done by the time school
[14:23] starts
[14:24] Again I'm available if other questions
[14:26] come up If not we'll see some people in
[14:30] two weeks
[14:32] Thanks everybody Appreciate it Again the
[14:35] patience why I signed on late today
Was this story helpful?
Other Topics from This Document
Vernon Avenue and Highway 100 interchange project status
Construction timeline and substantial completion date
Traffic control and pedestrian safety updates
Edina Liquor Store site work and temporary closure
Utility conflict with Xcel Energy power line
Noise wall construction and residential impact
Upcoming ramp closures and traffic detour modifications
School zone impacts during construction