Highway 100 Interchange Project Faces Bridge Delay
The Vernon Avenue and Highway 100 interchange project will not meet its November 15 completion deadline due to utility permit delays, Engineering Director Chad Milner announced during Thursday's bi-weekly project update.
The Vernon Avenue bridge over the CPKC rail line cannot be finished on schedule because Excel Energy and CPKC Rail have not secured necessary permits for utility line work. The power line was discovered in a different location than originally planned when it was struck in May, Milner said during the meeting.
"We have no control over these two agencies," Milner said. "This bridge will not be done November 15th. We're just past that timing now." The city has been waiting since May for the utility companies to resolve the permit issue, with initial expectations the work would be completed by mid-August.
Meanwhile, the project's most significant traffic impact begins September 15 when all Highway 100 off-ramps in the construction zone will close. The closures affect southbound traffic exiting at Arcadia and northbound traffic exiting at Grange Road, adding to existing restrictions. Highway 100 bridge beam installation continued this week with overnight work scheduled through Friday.
The city plans to support affected businesses through a "Worth the Detour" passport program launching September 15, offering customers loyalty stamps and gift card opportunities at participating Grand View and 50th and France district establishments. Despite the Vernon Avenue bridge delay, Milner said the Highway 100 bridge and ramps are expected to reopen on schedule.
Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.
Go deeper on this topic
Research related meeting documents and build a brief — without rewriting the story.
Full analysis
Areas of Interest (5)
- Infrastructure project faces indefinite delays due to inter-agency coordination failures between Xcel Energy and CPKC Rail.
- Major traffic disruptions expected starting September 15 as multiple Highway 100 off-ramps face total closure.
- Local business districts launch 'Worth the Detour' loyalty program to mitigate economic impact of long-term road closures.
- Project Director publicly criticizes utility agencies for stalling bridge construction, causing missing of key November deadline.
- Pedestrian safety concerns raised regarding increased school traffic on Benton Avenue near active construction zones.
Notable Quotes (3)
The Vernon Avenue bridge will not be done by November 15th.
Unless we learn something that this is going to be a much longer closure, at this point we're going to leave it as is.
Should have been corrected long time ago in my opinion and it's not.
People (1)
Chad MilnerEngineering DirectorLeading the Vernon Avenue/Highway 100 project and communicating status updates to the public.
2 quotes
Leading the Vernon Avenue/Highway 100 project and communicating status updates to the public.
“The Vernon Avenue bridge will not be done by November 15th.”
Admitting schedule slippage due to external agency delays.
“We're just in a waiting pattern. We're all contacting them.”
Describing the frustration regarding Xcel Energy and CPKC Rail permits.
Places Mentioned
Events & Meetings (2)
- September 15, 2025: Commencement of Stage 4 detours and ramp closures
- November 15, 2025: Planned substantial completion date (excluding Vernon Ave Bridge)
Source document
Was this story helpful?
Other Topics from This Document
Vernon Avenue and Highway 100 interchange project status
Construction safety and pedestrian traffic concerns
Project schedule delays due to Xcel Energy and CPKC Rail utility conflicts
Stage 4 detours and ramp closures beginning September 15
Business outreach and 'Worth the Detour' loyalty program
Highway 100 overhead sign maintenance update
5100 Eden Avenue development demolition updates
Construction progress on noise walls and retaining walls