StoryConstruction delays and upcoming major traffic impacts for Highway 100 interchange projectSeptember 4, 2025

Highway 100 Interchange Project Faces Bridge Delay

Meeting date: Sep 4, 2025
Published Sep 8, 2025

The Vernon Avenue and Highway 100 interchange project will not meet its November 15 completion deadline due to utility permit delays, Engineering Director Chad Milner announced during Thursday's bi-weekly project update.

The Vernon Avenue bridge over the CPKC rail line cannot be finished on schedule because Excel Energy and CPKC Rail have not secured necessary permits for utility line work. The power line was discovered in a different location than originally planned when it was struck in May, Milner said during the meeting.

"We have no control over these two agencies," Milner said. "This bridge will not be done November 15th. We're just past that timing now." The city has been waiting since May for the utility companies to resolve the permit issue, with initial expectations the work would be completed by mid-August.

Meanwhile, the project's most significant traffic impact begins September 15 when all Highway 100 off-ramps in the construction zone will close. The closures affect southbound traffic exiting at Arcadia and northbound traffic exiting at Grange Road, adding to existing restrictions. Highway 100 bridge beam installation continued this week with overnight work scheduled through Friday.

The city plans to support affected businesses through a "Worth the Detour" passport program launching September 15, offering customers loyalty stamps and gift card opportunities at participating Grand View and 50th and France district establishments. Despite the Vernon Avenue bridge delay, Milner said the Highway 100 bridge and ramps are expected to reopen on schedule.

Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.

Go deeper on this topic

Research related meeting documents and build a brief — without rewriting the story.

Full analysis
  • Infrastructure project faces indefinite delays due to inter-agency coordination failures between Xcel Energy and CPKC Rail.
  • Major traffic disruptions expected starting September 15 as multiple Highway 100 off-ramps face total closure.
  • Local business districts launch 'Worth the Detour' loyalty program to mitigate economic impact of long-term road closures.
  • Project Director publicly criticizes utility agencies for stalling bridge construction, causing missing of key November deadline.
  • Pedestrian safety concerns raised regarding increased school traffic on Benton Avenue near active construction zones.

The Vernon Avenue bridge will not be done by November 15th.

Chad Milner
Project scheduleAddressing project completion deadlines.

Unless we learn something that this is going to be a much longer closure, at this point we're going to leave it as is.

Chad Milner
Traffic managementExplaining the continued closure of Gus Young Lane.

Should have been corrected long time ago in my opinion and it's not.

Chad Milner
Project managementCommenting on the utility conflict timeline.
Source document

[0:00] Good morning everybody. Vernon Avenue

[0:02] and Highway 100 interchange project

[0:04] update meeting number 12. Just a

[0:07] reminder that we are recording these and

[0:09] we'll post them online afterwards. So

[0:12] I'm Chad Milner, engineering director.

[0:14] Thanks for joining us. Uh thanks for

[0:16] your patience. The project continues to

[0:18] move forward. Businesses are open and

[0:20] accessible. Of course with construction

[0:23] comes noise, dust, and vibrations. Um

[0:26] stop for pedestrians and crosswalks. We

[0:28] still have uh school started. So, we

[0:31] have a lot more people and kids and

[0:33] students using Eden Avenue, specifically

[0:36] Benton Avenue. There's crosswalks, kids

[0:38] going to school. Make sure we're being

[0:41] safe, courteous, and not only the

[0:43] pedestrians, but also the fellow

[0:45] drivers. So, please be patient. If

[0:48] you're not comfortable with that midb

[0:49] block crossing at uh Eden Avenue, please

[0:53] use the fully controlled traffic signal

[0:55] at Vernon and Eden instead.

[0:59] These are the project goals. Um again,

[1:02] it's to improve safety, mobility, create

[1:05] separated pedestrian routes, improve

[1:07] traffic operations,

[1:09] and the other ones there listed. We have

[1:12] the project schedule listed there. The

[1:14] com substantial completion date and

[1:17] reopening November 15, 2025. Um I can

[1:21] say that

[1:23] good good portion of the project will be

[1:25] reopened, but uh the Vernon Avenue

[1:27] bridge will not be done by November

[1:29] 15th. So that's an issue we'll talk

[1:31] about here a little bit more.

[1:34] This is the project again. It starts

[1:36] just west of Interlockan Boulevard. has

[1:38] the Vernon Avenue Bridge over the CPKC

[1:41] rail line. Then the Highway 100 bridge

[1:44] over Highway 100 that spans

[1:47] uh carries 50th Street and Vernon Avenue

[1:52] and then ends just near Graange Road on

[1:54] the east side.

[1:57] We've been doing all these communication

[1:59] channels for residents and businesses.

[2:02] uh continue to look for those, continue

[2:04] to push out that information. If people

[2:06] have questions, better together.org,

[2:10] visit the Vernon Highway 100 project

[2:12] page. That is your best spot to find

[2:15] information as we continue to move

[2:18] forward this fall.

[2:21] We have some big detours coming, so

[2:22] we're creating a special business

[2:26] outreach. So we want anybody that's

[2:28] associated with businesses to please

[2:30] fill out a survey. So go to this website

[2:33] edinaamn.gov

[2:36] businessup support and fill out the

[2:39] survey if you interested. But we are

[2:41] going to support the Grand View and 50th

[2:43] and France businesses this fall. We're

[2:45] going to have the worth the detour

[2:47] passport. So, it'll be a loyalty program

[2:50] where customers can collect stamps when

[2:52] you shop and dine at participating

[2:55] businesses and then enter to win gift

[2:56] cards at those favorite local spots. We

[3:00] want to thank the Explory Dina for their

[3:03] support.

[3:04] So, there's also going to be a

[3:06] restaurant week social media contest and

[3:09] a free familyfriendly movie on select

[3:13] Saturday mornings at the Dina Theater.

[3:15] So again, find all the details at better

[3:18] together.org. And if you're a specific

[3:20] business, go to that other website and

[3:22] fill out a survey. We did mail out

[3:24] letters to many of the businesses in

[3:27] both the Grand View and the 50th in

[3:29] France districts. So thank you and

[3:32] please fill out the survey.

[3:35] Construction details, uh, Interlock and

[3:37] Verdon, that's still a free flow

[3:39] intersection there. It's working and

[3:41] operating. We've got questions of can we

[3:44] open up Gus Young Lane by the Dino

[3:46] Liquor Store. We're hoping to have a

[3:48] crane there at any moment to start

[3:50] working on that west abutment. We did

[3:52] open it. We'd have to have either a

[3:54] four-way stop or a temporary signal. Um,

[3:58] and that would really, I think, impact

[4:00] traffic operations on this intersection.

[4:02] So unless we learn something that this

[4:04] is going to be a much longer closure, at

[4:08] this point we're going to leave it as is

[4:10] and prepare to place a crane and other

[4:12] equipment there to work on that west

[4:14] abutment.

[4:17] And why aren't we working on that west

[4:19] abupment? It's because the XL power line

[4:21] was as shown here and circled in green

[4:24] was in a different spot than originally

[4:27] uh thought. was hit in May and Excel

[4:31] Energy and TPKC Rail are continue to

[4:35] work on permits and agreements. We do

[4:36] not have it. They're working on it. I

[4:38] thought it would be done early to mid

[4:40] August. We have no control over these

[4:43] two agencies. Uh and it's major impact

[4:46] of schedule andor cost. and we still

[4:48] don't know what those are because until

[4:50] we actually get a permit and the

[4:52] contractor can start working. We can't

[4:55] put together any of those timing details

[4:57] or cost potential details. So, we're

[5:01] just in a waiting pattern. We're all

[5:03] contacting them. The mayor's contacting

[5:05] individuals. We're trying to get this

[5:07] move forward. um should have been

[5:10] corrected long time ago in my opinion

[5:12] and it's not and we're doing everything

[5:14] we can but this bridge will not be done

[5:16] November 15th. Uh we're just past that

[5:19] timing now. So until we know when this

[5:21] work can occur, updated schedules won't

[5:25] be developed. There's kind of

[5:27] potentially two options where they work

[5:30] uh straight through into the winter and

[5:33] heat and heat everything to do the

[5:35] concrete work, but there's a cost with

[5:37] that. order they go away and come back

[5:38] in the spring to finish. So, those are

[5:41] the two options we're looking at once we

[5:43] know when they can actually start.

[5:47] Road closures and detours. We have a big

[5:49] kind of the last detour stage four

[5:53] coming up. This is probably going to be

[5:54] the most impactful. Um and it's going to

[5:58] start on Monday, September 15th. So, all

[6:01] offramps

[6:03] are going to be closed on the 15th.

[6:08] So, if you're coming southbound on 100

[6:10] and use that Arcadia exit, that will be

[6:12] closed. That'll be a new closure. You're

[6:15] heading northbound and you take the exit

[6:17] to Graange Road, that will be closed.

[6:20] So, these three red X's will be new

[6:23] closures. The blue one was already been

[6:25] in place for a few weeks. We're updating

[6:28] our maps on the website and the

[6:29] interactive GIS map. Those will be

[6:31] updated soon. Um, but that's a big

[6:36] impact that's going to start September

[6:38] 15th and until until the mid- November

[6:42] date so they can build all these new

[6:43] ramps.

[6:45] What has been happening and will

[6:46] continue to happen this week is the

[6:48] Highway 100 bridge uh the gurners are

[6:50] going up the beams. So this first week

[6:52] of September been happening overnight.

[6:55] Northbound happened

[6:58] Tuesday and Wednesday night. Now

[7:00] southbound will happen Thursday and

[7:02] Friday night. So hopefully all the beams

[7:04] will be placed uh by this weekend.

[7:10] Uh again, we're going to create those

[7:12] detour maps for that stage four, but

[7:14] Benton Avenue, we've seen more traffic.

[7:15] We know the schools started Mindat

[7:18] turned the timing off on the on-ramp

[7:20] signal, so that helped a lot with some

[7:22] of those impacts. Uh the detours are

[7:24] going to be up to Excelsier and east and

[7:27] west down the highway 62 in east and

[7:30] west kind of the regional detours and

[7:32] there's going to be some more local

[7:33] detours. So look for those maps coming

[7:35] very soon on that stage 4 which starts

[7:38] in about a week and a half.

[7:41] We know there's a project going on

[7:43] Highway 100. This is a mindot

[7:44] maintenance project. They're doing

[7:46] overhead sign work. Um they closed the

[7:49] inside lanes. It's been closed for

[7:51] weeks. It's creating traffic issues.

[7:54] We ask when they're going to be done. It

[7:56] was anticipated to be done yesterday. I

[7:58] can't find anything whether it is or

[8:00] isn't done. Go to their website and that

[8:03] website hasn't been updated until August

[8:05] 12th. So, I haven't driven up there

[8:07] today. I don't know if it's closed or

[8:09] still underway. I'm hoping it's done um

[8:12] because that was creating some issues,

[8:14] but again, that's not related to our

[8:16] project at all. Um the timing is just

[8:19] unfortunate and MDOT's doing their

[8:21] maintenance work there on those overhead

[8:23] signs.

[8:26] Other things in the area. So 5100 even

[8:29] Eden Avenue. This was a development

[8:31] project. Last time or last couple

[8:33] meetings we talked about the sidewalk

[8:35] detour that's shown on the lefthand

[8:37] side. They built a temporary sidewalk on

[8:39] the west side of Arcadia and closed the

[8:41] sidewalk starting at the historic

[8:43] properties on the east side of Highway

[8:45] 100. The blue dash line is that detour

[8:48] for the sidewalks. They started demo on

[8:51] Tuesday. So, here's a picture where

[8:52] they're starting to bring that building

[8:54] down. That work has started this week to

[8:58] demo that existing 5100 building.

[9:03] In other pictures, uh this is the you're

[9:06] looking east

[9:08] by the Devanis. This is the Vernon

[9:10] Avenue bridge. You can see the east

[9:12] abupman is done and ready. Here's that

[9:15] west side. The old one is still in

[9:16] place. So that's a Excel power line and

[9:18] we're just waiting for that. So uh this

[9:21] is the major concern right now with

[9:23] schedule. This is a updated picture of

[9:26] that area.

[9:28] This is that free flowing intersection

[9:30] at Interlockan in Vernon that stays the

[9:32] same.

[9:34] This is the retaining wall at Hawthorne

[9:36] Court near the Hawthorne Apartment. So

[9:38] the picture on the left was from a few

[9:40] weeks ago. Picture on the right was a

[9:42] recent picture from this week. So, the

[9:44] wall construction keeps going forward.

[9:48] And then the overnight work that

[9:50] started, these are pictures from Tuesday

[9:52] night. So, uh, the left picture is, it's

[9:55] hard to see, but the crane is hoisting

[9:57] up those beams. This was the first one.

[10:00] Middle bottom picture is it's almost in

[10:03] place. And then a closeup of as they

[10:05] literally touch that down onto the

[10:07] abupments uh for that first first beam

[10:11] on Tuesday night.

[10:13] And then picture on the left is number

[10:15] two coming into place. You can see how

[10:17] they were hoisting that up with the

[10:18] crane in the background.

[10:20] Some other pictures where there's almost

[10:22] eight of them in place that night. So

[10:24] you can see the different all of them

[10:27] spanning northbound 100.

[10:32] And here's how they brought them in.

[10:33] They brought them in with a big long

[10:34] truck. The crane picks them off and then

[10:38] places them onto those abupments. So,

[10:42] northbound should be done. I haven't

[10:43] heard here this morning. Southbound,

[10:46] it's going to happen tonight, tomorrow

[10:47] night.

[10:50] Then here's what it looks like during

[10:51] the day. So, the picture on the left is

[10:53] those first eight placed on Tuesday

[10:56] night. And then the picture on the right

[10:59] is just a different view of showing

[11:00] those in place. And it's good to see

[11:03] shadows on the highway. That means the

[11:04] deck is starting to be constructed.

[11:09] The other major thing that's going on is

[11:10] that noise wall along the

[11:13] northbound on-ramp from 50th Street. So

[11:16] the picture on the left was from a few

[11:17] weeks ago. They were just getting

[11:18] started. Picture on the right, you can

[11:20] see all those concrete posts that are

[11:22] going to support that noise wall

[11:24] basically from Miniha Creek up to 50th

[11:26] Street. So they are continuing to put

[11:29] the poles in and then the planking will

[11:30] be coming in a few weeks and they'll

[11:33] start installing the planking on that

[11:35] noise wall.

[11:38] And then just another picture of the

[11:39] operations of installing those concrete

[11:42] noise wall posts.

[11:46] And then the graphics and rendering of

[11:47] what this will look like. So it's

[11:49] getting closer and closer all the time.

[11:51] You're getting to this for the high 100

[11:52] bridge. The picture on the left is a

[11:54] view of the of the deck of the Highway

[11:57] 100 bridge. The picture on the right is

[12:00] from the Highway 100 itself. as you

[12:03] would pass underneath the bridge heading

[12:04] northbound. You can start to see the

[12:06] beams that were placed the other night.

[12:08] Um, and this will be completely placed

[12:11] here over the next couple nights. So,

[12:12] we're starting to get to this image for

[12:14] the project.

[12:19] So, with that, I'll look at the chat. If

[12:21] people have questions, please enter them

[12:24] into the chat. I'm happy to answer those

[12:26] questions. You can always call me and

[12:28] email me or Derek. We're happy to answer

[12:30] questions, come visit with you, whatever

[12:32] the case may be. So, any questions?

[12:37] And I just remind any of the businesses

[12:40] if there's interest in participating in

[12:42] that worth the detour passport thing,

[12:45] may remember to fill out that survey

[12:48] so we know you're interested and we'll

[12:50] work with communications and get that

[12:52] started.

[12:57] Any questions?

[13:08] quiet group.

[13:10] See somebody type typing. So just wait a

[13:13] second.

[13:27] Uh looked like somebody was typing.

[13:28] Maybe not. Oh, look like it might be

[13:30] coming back.

[13:34] Uh even though let's see here's a

[13:36] question. Crane on Gus Young will wait

[13:40] and to agree then work will begin on the

[13:43] western abupment. Yeah, we no work can

[13:45] start. I mean, if we could have started,

[13:46] we would have had Excel move that line

[13:48] and we asked them to do it in May, just

[13:50] temporarily do something, but railroad

[13:53] wouldn't let them do it, and they

[13:54] weren't willing to work without a permit

[13:56] in the railroad. So, yeah, Gus Young

[13:58] will be for crane and other heavy

[14:00] equipment to build that western abupment

[14:02] soon as that permit is in hand between

[14:05] those two parties. Um,

[14:14] and even though that bridge may not be

[14:17] ready by November 15th, our intention is

[14:19] still to open up the Highway 100 bridge,

[14:22] the on andoff ramps there, the get

[14:24] everything active and operational along

[14:26] Highway 100 and open up as much as we

[14:28] can,

[14:30] as soon as we can. And then we'll deal

[14:32] with the Vernon Avenue Bridge and those

[14:34] schedules and that impact once we've

[14:37] finally learn more here between Excel

[14:39] and the railroad.

[14:46] Other questions,

[14:49] comments?

[14:53] Visit the website. We'll be updating

[14:54] some maps. Every time we do a big stage

[14:56] detour change, we send out specific maps

[15:00] to the businesses right at the area

[15:04] there. So, look for some of those emails

[15:05] coming from me. All those maps are

[15:07] posted on the website if other

[15:08] businesses just want to print those and

[15:10] give them to customers. Um, look for

[15:12] that passport program that we're

[15:15] creating right now for the businesses in

[15:17] both districts, Grand View and 50th in

[15:20] France.

[15:21] Um, but September 15th, it's going to be

[15:24] a big day when those ramps close early

[15:27] in the morning. People are going to have

[15:29] to find different routes to access this

[15:31] area. Benton Avenue will still have

[15:33] those the one off-ramp for southbound

[15:37] and on-ramp for northbound.

[15:40] But to get into these areas, you're

[15:41] going to have to come from Highway 62

[15:43] and either use the Valley View exit,

[15:46] France Avenue, or on the west side,

[15:48] Tracy Avenue or Gleon. Um on the north,

[15:52] Excelsier Boulevard coming down Wooddale

[15:55] or Brookside. So you're just going to

[15:57] have to use some other avenues. Blake

[15:59] Road and Interlockan from Hopkins is an

[16:01] option.

[16:05] So let your employees and customers and

[16:07] yourself find some routes there for

[16:10] September 15th.

[16:17] Other questions? I see somebody typing.

[16:21] Why wouldn't we open Gus Young until we

[16:22] have some kind of timing? Because we'd

[16:24] have to install a temporary signal andor

[16:28] four-way stops. And we think that would

[16:30] really gnarly up traffic even worse when

[16:34] we know that the hope is that there's a

[16:36] crane there very soon. So if it starts

[16:39] to become more long-term, then we'll

[16:41] look at potentially opening up Gus

[16:43] Young. But at this point, our hope and

[16:46] intention and the draft language we got

[16:48] from those two pe two agencies is that

[16:50] this is going to have a permit any day

[16:53] now. So um so it comes to

[16:58] construction needs for space and traffic

[17:01] operations of that intersection.

[17:04] Thanks for the question.

[17:12] Okay, again my info is on the website.

[17:16] There's further questions just send me

[17:17] an email or give me a call. Appreciate

[17:20] everybody's time. We'll get this posted

[17:22] and we'll post the slides on the website

[17:24] if you want to share that out with

[17:25] anybody at your organization.

[17:29] Thank you.

Was this story helpful?

Other Topics from This Document

  • Vernon Avenue and Highway 100 interchange project status

  • Construction safety and pedestrian traffic concerns

  • Project schedule delays due to Xcel Energy and CPKC Rail utility conflicts

  • Stage 4 detours and ramp closures beginning September 15

  • Business outreach and 'Worth the Detour' loyalty program

  • Highway 100 overhead sign maintenance update

  • 5100 Eden Avenue development demolition updates

  • Construction progress on noise walls and retaining walls