Published Jul 2, 2025

The City of Chanhassen has released an educational video explaining its pavement management plan, focusing on full depth reclamation as a key road repair technique for the city's 119 miles of streets.

Full depth reclamation, or FDR, involves grinding up existing asphalt and mixing it with the top portion of the aggregate base to create a new foundation layer. New asphalt layers are then installed on top, with excess recyclable material hauled away for use elsewhere.

The city uses this construction method when existing pavement shows significant deterioration and scores below 60 on the Overall Condition Index, a zero to 100-point scale used to rate road health. The city reviews and grades all roads every three years, prioritizing work based on available funding and condition scores.

According to the video, full depth reclamation is more expensive than mill and overlay techniques but less costly than total reconstruction, which requires additional improvements. The method allows the city to recycle existing materials while extending road life.

The educational video is part of a pavement management series available to residents. Additional information about city projects is available at chanhassenm.gov/projects.

Our proprietary artificial intelligence agent analyzed publicly available documents including meeting agendas, minutes, and transcripts to write this story to help inform local residents. Feedback helps us improve, so please consider rating how we did with the thumbs up or down below.

Go deeper on this topic

Research related meeting documents and build a brief — without rewriting the story.

Full analysis

Notable Quotes (3)

Full depth reclamation or FDR involves grinding up a road's existing asphalt and mixing it with the top part of the aggregate base to create a new base layer.

Pavement Management Plan: Full Depth Reclamation (FDR) Technique Explanation

We use this construction technique when the existing pavement shows signs of significant deterioration and generally scores below a 60 on the overall condition index a zero to 100 point scale we use to rate a road's health.

Pavement Management Plan: Full Depth Reclamation (FDR) Technique Explanation

Although this method is more expensive and extensive than the mill and overlay technique it avoids the more costly total reconstruction which involves various additional improvements.

Pavement Management Plan: Full Depth Reclamation (FDR) Technique Explanation

Ordinances & Resolutions (4)

Pavement Management PlanPlan

City's strategic plan for managing street upkeep, prioritizing road work, and scheduling construction and repairs.

Overall Condition Index (OCI)Other

A 0 to 100-point scale used to rate a road's health and determine eligibility for specific repair techniques like full depth reclamation.

Pavement Management SeriesOther

A series of informational videos providing more detail on road repair selection processes and techniques.

chanhassenm.gov/projectsOther

Official city website providing information about ongoing projects around Chanhassen.

Source document

Was this story helpful?

Other Topics from This Document

  • Chanhassen Pavement Management Plan and Full Depth Reclamation

Want to know when new stories arrive?

Enter your email to receive updates.

We will not use your email for any other purpose. You can unsubscribe at any time.